Framework for improving workflow stability: deployment of optimized capacity buffers in a synchronized construction production

Mehrdad Arashpour, Ron Wakefield, Nick Blismas, E. W. M. Lee

Research output: Contribution to journalArticleResearchpeer-review

Abstract

Construction sites are dynamic environments due to the influence of variables such as changes in design and processes, unsteady demand, and unavailability of trades. These variables adversely affect productivity and can cause an unstable workflow in the network of trade contractors. Previous research on workflow stability in the construction and manufacturing domains has shown the effectiveness of ‘pull’ production or ‘rate driven’ construction. Pull systems authorize the start of construction when a job is completed and leaves the trade contractor network. However, the problem with pull systems is that completion dates are not explicitly considered and therefore additional mechanisms are required to ensure the due date integrity. On this basis, the aim of this investigation is to improve the coordination between output and demand using optimal-sized capacity buffers. Towards this aim, production data of two Australian construction companies were collected and analyzed. Capacity and cost optimizations were conducted to find the optimum buffer that strikes the balance between late completion costs and lost revenue opportunity. Following this, simulation experiments were designed and run to analyze different ‘what-if’ production scenarios. The findings show that capacity buffers enable builders to ensure a desired service level. Size of the capacity buffer is more sensitive to the level of variability in contractor processes than other production variables. This work contributes to the body-of-knowledge by improving production control in constructionanddeploymentof capacity buffers to achieve a stableworkflow.In addition, constructioncompaniescanuse the easy-to-use framework tested in this study to compute the optimal size for capacity buffers that maximizes profit and prevents late completions.

Original languageEnglish
Pages (from-to)995-1004
Number of pages10
JournalCanadian Journal of Civil Engineering
Volume41
Issue number12
DOIs
Publication statusPublished - 1 Dec 2014
Externally publishedYes

Keywords

  • Analytical modelling
  • Capacity buffer
  • Construction
  • Cost optimization
  • Discrete event simulation
  • Productivity
  • Pull workflow
  • Queue
  • Time series analysis
  • Under-capacity planning and scheduling

Cite this

@article{8a1a154203304d2797c9d21e19dae0a2,
title = "Framework for improving workflow stability: deployment of optimized capacity buffers in a synchronized construction production",
abstract = "Construction sites are dynamic environments due to the influence of variables such as changes in design and processes, unsteady demand, and unavailability of trades. These variables adversely affect productivity and can cause an unstable workflow in the network of trade contractors. Previous research on workflow stability in the construction and manufacturing domains has shown the effectiveness of ‘pull’ production or ‘rate driven’ construction. Pull systems authorize the start of construction when a job is completed and leaves the trade contractor network. However, the problem with pull systems is that completion dates are not explicitly considered and therefore additional mechanisms are required to ensure the due date integrity. On this basis, the aim of this investigation is to improve the coordination between output and demand using optimal-sized capacity buffers. Towards this aim, production data of two Australian construction companies were collected and analyzed. Capacity and cost optimizations were conducted to find the optimum buffer that strikes the balance between late completion costs and lost revenue opportunity. Following this, simulation experiments were designed and run to analyze different ‘what-if’ production scenarios. The findings show that capacity buffers enable builders to ensure a desired service level. Size of the capacity buffer is more sensitive to the level of variability in contractor processes than other production variables. This work contributes to the body-of-knowledge by improving production control in constructionanddeploymentof capacity buffers to achieve a stableworkflow.In addition, constructioncompaniescanuse the easy-to-use framework tested in this study to compute the optimal size for capacity buffers that maximizes profit and prevents late completions.",
keywords = "Analytical modelling, Capacity buffer, Construction, Cost optimization, Discrete event simulation, Productivity, Pull workflow, Queue, Time series analysis, Under-capacity planning and scheduling",
author = "Mehrdad Arashpour and Ron Wakefield and Nick Blismas and Lee, {E. W. M.}",
year = "2014",
month = "12",
day = "1",
doi = "10.1139/cjce-2014-0199",
language = "English",
volume = "41",
pages = "995--1004",
journal = "Canadian Journal of Civil Engineering",
issn = "0315-1468",
publisher = "NRC Research Press",
number = "12",

}

Framework for improving workflow stability : deployment of optimized capacity buffers in a synchronized construction production. / Arashpour, Mehrdad; Wakefield, Ron; Blismas, Nick; Lee, E. W. M.

In: Canadian Journal of Civil Engineering, Vol. 41, No. 12, 01.12.2014, p. 995-1004.

Research output: Contribution to journalArticleResearchpeer-review

TY - JOUR

T1 - Framework for improving workflow stability

T2 - deployment of optimized capacity buffers in a synchronized construction production

AU - Arashpour, Mehrdad

AU - Wakefield, Ron

AU - Blismas, Nick

AU - Lee, E. W. M.

PY - 2014/12/1

Y1 - 2014/12/1

N2 - Construction sites are dynamic environments due to the influence of variables such as changes in design and processes, unsteady demand, and unavailability of trades. These variables adversely affect productivity and can cause an unstable workflow in the network of trade contractors. Previous research on workflow stability in the construction and manufacturing domains has shown the effectiveness of ‘pull’ production or ‘rate driven’ construction. Pull systems authorize the start of construction when a job is completed and leaves the trade contractor network. However, the problem with pull systems is that completion dates are not explicitly considered and therefore additional mechanisms are required to ensure the due date integrity. On this basis, the aim of this investigation is to improve the coordination between output and demand using optimal-sized capacity buffers. Towards this aim, production data of two Australian construction companies were collected and analyzed. Capacity and cost optimizations were conducted to find the optimum buffer that strikes the balance between late completion costs and lost revenue opportunity. Following this, simulation experiments were designed and run to analyze different ‘what-if’ production scenarios. The findings show that capacity buffers enable builders to ensure a desired service level. Size of the capacity buffer is more sensitive to the level of variability in contractor processes than other production variables. This work contributes to the body-of-knowledge by improving production control in constructionanddeploymentof capacity buffers to achieve a stableworkflow.In addition, constructioncompaniescanuse the easy-to-use framework tested in this study to compute the optimal size for capacity buffers that maximizes profit and prevents late completions.

AB - Construction sites are dynamic environments due to the influence of variables such as changes in design and processes, unsteady demand, and unavailability of trades. These variables adversely affect productivity and can cause an unstable workflow in the network of trade contractors. Previous research on workflow stability in the construction and manufacturing domains has shown the effectiveness of ‘pull’ production or ‘rate driven’ construction. Pull systems authorize the start of construction when a job is completed and leaves the trade contractor network. However, the problem with pull systems is that completion dates are not explicitly considered and therefore additional mechanisms are required to ensure the due date integrity. On this basis, the aim of this investigation is to improve the coordination between output and demand using optimal-sized capacity buffers. Towards this aim, production data of two Australian construction companies were collected and analyzed. Capacity and cost optimizations were conducted to find the optimum buffer that strikes the balance between late completion costs and lost revenue opportunity. Following this, simulation experiments were designed and run to analyze different ‘what-if’ production scenarios. The findings show that capacity buffers enable builders to ensure a desired service level. Size of the capacity buffer is more sensitive to the level of variability in contractor processes than other production variables. This work contributes to the body-of-knowledge by improving production control in constructionanddeploymentof capacity buffers to achieve a stableworkflow.In addition, constructioncompaniescanuse the easy-to-use framework tested in this study to compute the optimal size for capacity buffers that maximizes profit and prevents late completions.

KW - Analytical modelling

KW - Capacity buffer

KW - Construction

KW - Cost optimization

KW - Discrete event simulation

KW - Productivity

KW - Pull workflow

KW - Queue

KW - Time series analysis

KW - Under-capacity planning and scheduling

UR - http://www.scopus.com/inward/record.url?scp=84914144767&partnerID=8YFLogxK

U2 - 10.1139/cjce-2014-0199

DO - 10.1139/cjce-2014-0199

M3 - Article

VL - 41

SP - 995

EP - 1004

JO - Canadian Journal of Civil Engineering

JF - Canadian Journal of Civil Engineering

SN - 0315-1468

IS - 12

ER -